Set up, protections and demolition |
 |
9 days |
 |
| |
Rough carpentry (framing) |
 |
8 days |
|
| |
Rough utilities (electric, plumbing and HVAC) |
 |
15 days |
|
| |
Exterior carpentry, stucco |
 |
8 days |
|
| |
Insulation and sheetrock (or plastering) |
 |
6 days |
|
| |
Finish carpentry including cabinets
|
 |
15 days |
|
| |
Tiling |
 |
5 days |
|
| |
Painting |
 |
11 days |
|
| |
Finish utilities (electric, plumbing fixtures installed)
|
 |
4 days |
|
| |
Flooring |
 |
2 days |
|
| |
Clean up |
 |
2 days |
|
| |
Total: |
 |
85 days or 17 work
weeks |
|
Some of this work is done concurrently this
type of kitchen remodel would typically be done in 12 to 14 weeks. |
 |